Freitag, 15. September 2017

The Dynamic Revetment is here!

Today's the day, what we've all been waiting for, the dynamic revetment!
We no longer need to stop and start all the instruments, therefore completing the profiles in-between each run goes a lot faster! So fast, that we are ahead of schedule again, completing all of DR1.
This meant we also had time to attempt the first trial of using the antenna to locate the pebbles in the revetment.
For those of you who are unaware, I shall quickly explain how this part of the experiment works.
The dynamic revetment consists of 9 m^3 pebbles, 5 m long shore and 7 m cross-shore (fig.1). This is meant to act as a defence from storms along the coast. The reason why it is called 'dynamic' is because (hopefully) the waves are meant to crash onto the revetment causing the pebbles to roll back landwards. Therefore the revetment is self maintained, causing it to be a cheaper alternative sea defence in the future. We have 97 seperate pebbles which have been painted either green (layer 1), orange (layer 2) or pink (layer 3). These pebbles have been implemented into the cross-shore center line of the revetment, depending on which layer they are in (either 1, 2 or 3). Each of these pebbles have a transponder located inside (so we can use the antenna to detect and locate them). These pebbles will then represent each layer of the dynamic revetment (dynarev), and hopefully we will be able to track where they move. This process will be done at the end of each test e.g. DR1, DR2 etc.

Fig.1 - The dynamic revetment in all its glory (yellow line indicating the crest of the revetment). You can just about see the green pebbles dotted around in the middle cross-shore section. 

Fig.2 - The green pebbles with transponders located inside.

Fig.3 - After a few hours of waves- loosing quite a few pebbles to the flume!

Fig.4 - Paul fixing the reader for the transponders,
 after he managed to drop it...not to worry everyone, it still works!

Fig. 5 - Paul attempting to locate the pebbles, the long pole is proving difficult to control.

Fig. 6 - Jens came up with the brilliant idea of attaching some rope to the end of the antenna and hold it the other side of the flume to support the pole, preventing it from wobbling around - worked a treat!

Mittwoch, 13. September 2017

Deconstruction of rigs/Construction of revetment

Today was a sad day...We had to pack all of our equipment away. It has been a long 5 weeks and it certainly felt strange not turning on any of the laptops or instruments!
So, we had two groups of people, one working in the flume dismantling the rigs whilst the others were building the revetment at the top of the beach. All exciting stuff!
By the end of the day, everything was packed in boxes, and the revetment was up and running ready for waves tomorrow. Hopefully we have packed everything correctly and not left anything behind...! (Peter don't worry we definitely do have everything packed cleaned, dried and bubble wrapped! Aaron made sure of that) - if anything happens blame the shipping!
Anyway, everything is done...it is beer o'clock!

Before the destruction began!

All instruments and cables all dismantled,
 ready to be cleaned and packed.

Emily and Jak removing the final instrument, 3D sonar scanner.

And that's it, everything has been packed!


The revetment is in!



Even at home the work continues...Did someone say Matlab?

Dienstag, 12. September 2017

DR0 - completed!


Today the final set of tests for rig 1 and 2 were completed (DR0 - 20 hours), and the instruments logged for the final time. 
Half way through the test the vectrinos were buried, and we jumped into the freezing flume (for the last time-Yay!). We rotated the clamps up, rising the entire rig. All the equipment actually worked, apart from the final 3 hour run, our ABS would not respond...obviously something had to fail. On a positive note, the profiles came out looking pretty good (fig.1). When comparing test SB0_14 to DR0_14 (fig.3), which is the final profile of the tests, they should be identical (in theory) due to it being the same test being repeated. In general the profile is very similar, and only significantly differs ~235 m where SB0 has bedforms and DR0 has an inner sand bar.
So, apart from that me and Emily are done and dusted for our part of the experiment. We were joined by two more people from Plymouth Uni, Jak and Aaron, to help dismantle and pack everything from rig 1 and 2, ready to be shipped back to the UK. 


Fig 1 - Me and Paul braving the water for the final time!

Fig.2 - Cross-shore profile of test DR01 to 14. An increase in erosion is occurring on the beach-face, moving the sediment offshore, increasing the size of the sand bar. 

Fig.3 - Cross-shore profile of SB0_14, DR0_14 and the original profile of SB0. These two profiles have had the same time length of waves (20 hours), so in theory they should be the same. 

Freitag, 8. September 2017

Phase 2 of DynaRev

DR0 waves are running today, and on the whole it went smoothly! After lunch the vectrinos decided to bury themselves in the sediment, time to jump in again... However, after 4 weeks of wading into this freezing cold murky river water, Jen came down and said he had some waders. Where were these at the beginning?! Sorry Daniel and Gerd for sacrificing yourselves to the water, we had waders the whole time...Oh well, better late then never, thank you Jen! I definitely rocked the outfit.
We are still ahead of schedule, completing 4 hours of waves (fig.2) so we can relax over the weekend... We will continue DR0 on Monday.  

Figure 1 - Me getting ready to do some DIY on rig 1.

Figure 2- Original cross-shore profile including profile DR0-7, the last run of today (4 hours). The sandbar is already taking shape and the beachface has begun to erode.

Figure 3 - Schematic diagram of the DynaRev experiment, including rig 1 and 2, 3D scanner, LiDARS, ADVs, an original beach profile and a profile from SBO-14, to get a visual of where the instruments are in respect to the sandbar. 





Donnerstag, 7. September 2017

Re-shaping


So the last two days we've had 'off', and when I say off we actually had to move a tonne of sediment! But it was nice to do something different. So we have re-shaped the beach back to how it was originally (or as close as we could get to it), and we shall be running wave SB0 again (but this time it's called DR0, Dynamic Revetment). Once this has been completed and we're happy that the beach is stable the revetment, finally, can be installed! All the tests we completed in the first half of the experiment will be done again, but obviously with the revetment in place this time, and this is so we can compare the two beaches (one with the revetment, one without).
And just like magic...(or 13 hours of manual labour) the beach is flat as a pancake, instruments have been re-measured and tightened, ready for waves in the morning! 










Dienstag, 5. September 2017

After the storm


Sandy Beach Accretion waves (SBA1). (SRP) This morning on rig 1, as it had ended up being down, I jumped in the flume once again. The water temperature is not getting any warmer, no surprise, it is refreshing when I come out! SRP fixed, time to carry on with wave run SBA1, and just in time for lunch!
Looks like all this data collection is taking its toll on someone! 
Figure 1,2,3 (SB1, SBE1, SBE2 and SBA1), you can see the beach profile changing over time. As expected, the erosive waves (SBE) significantly erode the beach face. The sandbar builds up and SBE waves. SBA waves cause it to be erode but ripples form in its place.
This is one of the most important aspects of the experiment. Fingers crossed all goes to plan!
Figure 1 -Cross-shore profile of the beachface. Includes the first full profile of the experiment (blue). Up to a meter of sand has eroded over the course of the experiment. 

Figure 2 - Cross-shore profile of the sandbar. Sandbar is migrating offshore and accreting waves are causing the bar to erode and form ripples.
Figure 3 - Overall cross-shore profile. You can see an inner trough forming at ~254 m as a result of accreting waves.













Montag, 4. September 2017

Storm a-brewin'



Wave runs SBE1 and SBE2 (Sandy Beach Erosion) commenced today. The wave height (originally 0.8 m) increased to 1.0, then to 1.2 m, with an increasing wave period (originally 6.0 s) of 7.0 to 8.0 s. Very exciting stuff! In the video below, a very large wave breaks at around 38 seconds in. 
Everything was going smoothly, the waves were getting higher and we were running ahead of schedule. However, obviously, this would not last long as we managed to over heat the wave paddle and break it. I guess we will not be getting those 1.3 m waves ...
Nonetheless the wave paddle trooped on with 1.2 m waves and the profiles were as expected. Erosion occurred after each run on the beach face (fig. 2) , and the sand bar is migrating seawards (fig.3).  Now that the waves are bigger, water depth has decreased at the sand bar, therefore when the waves break, this energy from the undertow forces sediment back (seawards), hence why we can see the bar gradually retreating. 
The OBS's on rig 2 have also gone a bit crazy, and the data produced looked as if something was blocking the sensors. Reluctantly I jumped into the FREEZING water and i couldn't find anything wrapped around it. However, there were quite a few pebbles on the seabed, meaning they could be being suspended up by the current  or the instruments are being bombarded by pebbles. Either way, hopefully tomorrow we shall get some nice data completing tests Sandy Beach Accretion (SBA1), and we'll try not to break the wave machine!
Figure 1 - Full cross-shore profile.
Figure 2 - Cross-shore profile of the beach face, eroding with every run. (BE11 to 13 = SBE 1) (BE14 to 18 = SBE2).

Figure 3 - Cross-shore profile of the sand bar, showing the front of the bar is eroding and the back of the bar is accreting, migrating seaward